Friday, 27 February 2015
Overnight closures to Market Street
Ringway have a blog to keep us up to date on the happenings.
Thursday, 24 June 2010
Toilet back after 3 years.
It is now nearly 3 years since the Market Street wall collapsed after flash flooding in July 2007. The sluice valves that should have allowed the water to escape into the brook had not been maintained and had rusted closed. With nowhere to go the pressure and weight of the water caused the wall to collapse.
Read the full history of the wall (according to me)
Monday, 5 January 2009
Wall's vital statistics called into question.
Questions were also raised about the missing drop kerb for the zebra crossing, the installation of a road sign with the support in the middle of the pathway, the quality and finish of the paving and various other questions.
One rumour that was squashed was that the missing coping stone hadn't been removed by New Year revellers, but had been sent away to be machine cut to fit the remaining gap.
Friday, 14 November 2008
Countdown to Christmas
The countdown to Christmas started tonight in Tenbury Wells with the switching on of the new Christmas Street decorations.Saturday, 4 October 2008
Toilet Design Competition - Result

Tenbury Mayor, Cllr Richard Jones, and District Cllrs Phil Grove & Tony Penn pose for photographs with the Project Manager and the Architect of the winning design.The winning design emerged as clear favourite during the public consultation exercise held earlier this year. Following meetings with the planners, conservation officer and other council officials it was agreed that the popular design was suitable and could be built.
MHDC Press Release
Tenbury Advertiser
Friday, 3 October 2008
Market Street Wall - Progress
Tuesday, 9 September 2008
Tenbury standing by.
With heavy rain forecast for Thursday a temporary sandbag wall has been erected at the Market Street Wall Works.This is try to stop water spilling from the Brook into Market Street should the heavy rain cause the waters to rise.
Market Street Wall - Progress
(Click on link below)
Saturday, 6 September 2008
Lucky Escape
As Fire Crews clean the roads this morning, must shopkeepers appear to have had a lucky escape. The water in Market Street peaked mid-evening last night and only Caldicott Home Centre and The Little Fish Shop appear to have been flooded.
Friday, 5 September 2008
The Wall - The history according to me!
Lack of action by the local authorities in shoring up the bank meant that when the second flood followed a few days later, the wall foundations were undermined and the 'float foundation' of the newly refurbished toilets were washed out causing the toilets to subside.
Although the toilets were not damaged, the local authorities decided that it would be easier and cheaper to demolish them rather than try to jack them up a save them.
Months of confusion followed as none of the authorities wanted to take responsibility for the site. The wall was the responsibility of the County Council as it protected the road. The toilets were the responsibility of the District Council. Anything affecting the water course is the responsibility of the Environment Agency, and the Town Council take a view on all things local.More delays followed whilst contractors submitted their estimates and project plans.
Now more than 12 months later the work to replace the wall has only just started. The work was expected to be completed by Christmas but this is now in doubt as the latest flood has washed away the wooden form-work and has more than likely made the site unstable. Depending on what has been washed away, there is a possibility that the road may have been further damaged.
Tenbury Wells was flooded three times in Summer 2007
25th June at approx. 18.00 hrs
17th July at approx. 14.45 hrs
20th July at approx. 18.00 hrs
and now September 5th at approx. 18.00 hrs
Click here for more.
What a difference 24 hours makes.
Tenbury Mayor; Cllr Jones, Cllr Morgan and Town/District Councillor Penn take a break in their sandbag distribution to survey the damage.Less than 24 hours after their meeting with the Environment Agency, where it was confirmed that Tenbury would not be getting any flood defences, Town, District and County Councillors were out in force on the flooded streets of Tenbury.
The Tenbury Crisis Management Team and Plan were swung into action early this evening as it became clear that Kyre Brook would breach its banks.
Click here for more.
Avoidable Flood Hits Market Street
Thursday, 31 July 2008
Contractors press ahead.
The traffic lights have been removed as promised to allow the free movement of traffic during the Show weekend.
Tuesday, 15 July 2008
Wall works stall
A few workmen were sighted later in the day, but despite all the assurances that the work would be completed as soon as possible and that WCC were very happy with the work schedule, remarkably little activity has been seen so far!
Monday, 14 July 2008
Wall works start.
Tuesday, 8 July 2008
Wall work to start
Local contractor, Alun Griffiths Civil Engineering, have committed to finishing the work by Christmas.Two way temporary traffic signals will be in operation, throughout the duration of the works but WCC have asked that they be withdrawn when possible.
MHDC Conservation Officer has specified that the new brickwork and coping stones should match the original wall with as many stones as possible being recovered from the brook and reused.
The initial phase of the work will be to stabilise the bank, which was weakened and damaged by the over enthusiastic, and some would say, unnecessary demolition of the late Victorian toilet block also damaged by flood water.
Tenbury Advertiser Article
Letter to Tenbury Advertiser
Monday, 7 April 2008
Town Council blamed for wall delay.
Three months to the day after I wrote to the Town Council to say that the Environment Agency would not accept their proposal to culvert Kyre Brook, it was finally confirmed at tonight's meeting that the idea would now be dropped.
The WCC Engineer who addressed tonight's meeting claimed that had it not been for the insistence by the Town Council that they pursue this idea, the replacement wall would now be in place.
WCCs remit is to build a wall to support the highway, and flood defences are the responsibility of the Environment Agency. WCC have therefore not undertaken any flood modelling or flow rate monitorin, as they do not require this data to replace the wall. The Environment Agency have recommended that WCC rebuild the wall to a height slightly higher than last years maximum flood level, but no thought seems to have been given to where the water will go, or to the fact that the new wall will join a lower wall, thereby cancelling out any flood defence benefits.
WCC have just appointed new contractors for all engineering work and will now be submitting the plans to these contractors for comments and estimates. It is unlikely that the work will now commence before July.
Councillors at tonight's meeting expressed surprise that as they have do not have sufficient technical qualifications or knowledge to know if the proposed scheme is technically correct, that WCC were waiting for them to sign off the project.
Ludlow Journal
Monday, 3 March 2008
Replacement Wall Still Under Discussion
Concerns were also raised about the narrow scope of the project, which could lead to water flow being diverted in such a way to undermine the foundations of adjacent buildings or eroding the opposite bank leading to collapse and possible total blockage of the brook.
Again due to the lack of joined up thinking, the proposed wall which appears to be 5ft high, is higher than, and does not join up to the next section of the wall on private ground.
The Town Council's proposed solution is to culvert the brook along this section, creating a market square and access to a small park on the opposite bank of the brook. This suggestion has met with fierce opposition from the residents whose properties would adjoin the park, and from the Environment Agency who have a policy of objecting to culverts.
A meeting is to be held later this week to begin the process of planning the replacement toilets, but it seems that due to what appears to be an incredible lack of momentum by Worcestershire County Council, the fundamental questions about the flood defences have yet to be met.
Tuesday, 19 February 2008
Market Street Update
(Updated 02/03/08)
| Name | Business | Trading | Refurbished | Comments |
| Marilyn Ladies Fashions | 26, Market St, 01584 811662 Clothes Shops - | Yes | Yes | Reopened late October |
| The Barn Shop | Fruit, Veg & Plants | Yes | Yes | Reopened early August |
| The Little Fish Shop | Wet Fish Sales | Yes | Yes | Opened Feb 08 |
| Pet Shop | 18, Market St, Pet Shop | Yes | Yes | Reopened Late November |
| Sue Ryder | Charity Shop | Yes | Yes | Reopened 19th September |
| The Hair Shop | 16, Market St, 01584 819564 Hairdressers | Yes | Yes | |
| Phil @ The Clockhouse | Deli & Butchers | Yes | Yes | Reopened Late November |
| Whites @ The Clockhouse | Restaurant | Yes | Yes | |
| Royal Oak | Pub | Yes | Yes | Reopened 12th November |
| Singapore Restaurant | 6-8 Market St, Chinese Restaurant | Yes | Yes | Reopened Feb 08 |
| The Spotty Dog | Tea Room | Yes | Yes | |
| St Michaels Hospice | 1-2 Market St, 01584 819898 Charity Shop | No | Started | No Floor open to cellar New Floor layed Feb 08 |
| Richard C Swift Ltd | Bakers | No | Started | No Floor open to cellar New Floor layed Feb 08 |
| Ruffles | Curtain Shop | Yes | Yes | Fully reopened Jan 08 |
| Yuh Wah | 17 Market St, 01584 810885 | Yes | No | Not Flooded |
| Caldicott | 15 Market St, 01584 810281 Funeral Directors | Yes | Yes | |
| Caldicott | 15 Market St, 01584 810561 Builders Merchant | Yes | Yes | |
| Femina Hair Styles | 9, Market St, 01584 810107 Hairdressers | Yes | Yes | |
| The Embroidery Shop | 7, Market St, 01584 810906 Needlecraft Retailers | No | In Progress | Due to reopen March 08 |
| Mr Bens | Gents Barbers 5, Market St, | Yes | Yes | Opened as Gents Barbers Jan 08 |
| Country Flowers | 5, Market St, 01584 819446 Florist | Yes | Yes | Opened Feb 08 |
Monday, 28 January 2008
Market Street Wall - Update
The original project plan of 6 months with extended periods of road closures has been reduced to
- unknown (no final agreement, but less than 6 months)
- no lengthy closures (may be a few overnight closures)
- two way (not three way) lights
- no access required from Greenhill Close
A few fundamental flaws have been identified, such as
- the wall isn't long enough. There is a gap between Caldicott's and the wall.
- the wall on the opposite bank is also damaged.
- what effect the change in flow might have on the down stream building foundations.
Tenbury Town Council is still pursuing their preferred option of culverting the brook in this area, although this
- is against the Environment Agencies Policy,
- may lead to additional delays,
- is uncosted,
- is opposed by local residents,
- will cause a restriction due to the finite capacity of any culvert.