150 or so local people, including some Town Councillors, Shopkeepers, and representatives from the Emergency Services gathered at Tenbury High School on Wednesday to hear the County Council's briefing about the closure of Teme Bridge for repairs.
The meeting was rather light on information, as much of what was revealed was already well know locally.
The only bit of "news" was that English Heritage had refused permission for the upstream pavement to be removed, so the planned widening will no longer happen.
The bridge is expected to be closed for up to five months from 9th January, although it was hoped that it would be possible to use the bridge for periods during that time. A footpath would be maintained during the closure period and a temporary car park will be established on the North side of the bridge.
The contractor will be chosen not on a least cost basis, but one who can finish the work quickly and can make the bridge available for traffic for as much of the time as possible. Full details of all these arrangements should be available by mid November, once the contractor had been appointed.
It was explained that the bridge needed repairing and that as it no longer met the statutory requirements additional works would be carried out to bring the bridge up to specification. It was hoped that these repairs would be the last major repairs for the next 120 years.
There had been calls for the repairs to be shelved, and have a weight limit instead, but it was explained that this would only delay the need to spend even more money in the future and weight limits are virtually unenforceable.
The Council also commented on the idea of a new bridge, but said that they didn't have access to the necessary £8 to £10 million pounds, and that the bridge would have to be sited much further up or down stream as it would not be allowed within sight of the old bridge, and the old bridge couldn't be demolished.
There were calls from the floor for a temporary bridge to be installed during the work which could be funded by tolls. Again the Council explained that they hadn't the money for a temporary bridge.
A shop keeper asked if they would get compensation for the loss of trade, but was told that no compensation would be available, although there might be the possibility of some rate relief.
The Council said that all the diversionary routes would be gritted in the event of bad weather. Separate routes would be sign posted for HGVs.
The Fire & Rescue Service will station an engine at the Bromyard Road Business Park during the closure.
Ambulance control will ensure cover is available via the diversionary routes or from Leominster or Bromyard. The Police will have an additional vehicle available in Tenbury.